jain.com

Delta Forge 2 compute capacity

Company: Applied Digital - Project: Delta Forge 2

Subject kind
facility capacity
Statement date
2026-10-02
Promised amount
210.0 MW
Current status
stated

The claim, verbatim

The campus will be a single AI factory building running up to 210 megawatts of computing capacity.

Source (primary)

Applied Digital Pledges Partnership at First Town Hall on $3.2 Billion Brookwood Data Center - Tuscaloosa Thread (-, news_article)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “running up to 210 megawatts of computing capacity”

How we checked this

Checked on October 5, 2026. The cited source supports every part of this claim.

The article states the campus will be a single AI factory building running up to 210 megawatts of computing capacity.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://tuscaloosathread.com/applied-digital-brookwood-town-hall/) in full (13,670 characters, retrieved October 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital Pledges Partnership at First Town Hall on $3.2 Billion Brookwood Data Center - Tuscaloosa Thread

Quote: “running up to 210 megawatts of computing capacity”

View cached copy (2026-10-03)Live source ↗Archive.org ↗