Delta Forge 2 hyperscaler lease

Company: Applied Digital - Project: Delta Forge 2

Subject kind
customer
Statement date
2026-07-27
Promised by
2028-06-30
Promised amount
5200000000.0 USD
Current status
stated

The claim, verbatim

Signed a third 15-year take-or-pay lease with the same hyperscaler for 210 MW at Delta Forge 2 in a new southern state, providing approximately $5.2 billion in base-term contracted revenue, with initial operations expected in the first half of calendar 2028.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Signed a third 15-year take-or-pay lease with the same high investment-grade hyperscaler for 210 MW at Delta Forge 2 (fifth AI Factory campus, third consecutive with this customer) in a new southern state. The lease provides for approximately $5.2 billion in base-term contracted revenue, with initial operations expected in the first half of calendar 2028.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release's subsequent-events section states each of these Delta Forge 2 lease terms.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/159/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (55,619 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Signed a third 15-year take-or-pay lease with the same high investment-grade hyperscaler for 210 MW at Delta Forge 2 (fifth AI Factory campus, third consecutive with this customer) in a new southern state. The lease provides for approximately $5.2 billion in base-term contracted revenue, with initial operations expected in the first half of calendar 2028.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2026-07-27.