jain.com

Delta Forge 2 critical IT load

Company: Applied Digital - Project: Delta Forge 2

Subject kind
facility capacity
Statement date
2026-06-08
Promised amount
210.0 MW
Current status
stated

The claim, verbatim

Delta Forge 2 campus contains 210 MW of critical IT load.

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-06)Live source ↗

Quote: “The agreement covers 210 MW of critical IT load under a 15-year take-or-pay structure”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “The agreement covers 210 MW of critical IT load under a 15-year take-or-pay structure”

View cached copy (2026-09-06)Live source ↗