jain.com

210 MW IT load capacity at Delta Forge 2

Company: Applied Digital - Project: Delta Forge 2

Subject kind
facility capacity
Statement date
2026-08-20
Promised amount
210.0 MW
Current status
stated

The claim, verbatim

Applied Digital's Delta Forge 2 campus will deliver 210 megawatts of critical IT load

Source (primary)

Tiger Global Takes New Position In Applied Digital (NASDAQ: APLD) As AI Data Center Demand Surges - foreignpolicyjournal.com (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “The deal covers 210 megawatts of critical IT load at Delta Forge 2”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states the deal covers 210 megawatts of critical IT load at Delta Forge 2.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.foreignpolicyjournal.com/2026/08/20/tiger-global-takes-new-position-in-applied-digital-nasdaq-apld-as-ai-data-center-demand-surges/) in full (3,156 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Tiger Global Takes New Position In Applied Digital (NASDAQ: APLD) As AI Data Center Demand Surges - foreignpolicyjournal.com

Quote: “The deal covers 210 megawatts of critical IT load at Delta Forge 2”

View cached copy (2026-08-31)Live source ↗