jain.com

Delta Forge 2 operations commencement

Company: Applied Digital - Project: Delta Forge 2

Subject kind
facility timeline
Statement date
2026-06-08
Current status
stated

The claim, verbatim

Initial operations at Delta Forge 2 are anticipated to commence in Q1 2028.

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-06)Live source ↗

Quote: “Initial operations are anticipated to commence in Q1 2028.”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states initial operations are anticipated to commence in Q1 2028.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315226027984/ex99-1.htm) in full (9,210 characters, retrieved September 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “Initial operations are anticipated to commence in Q1 2028.”

View cached copy (2026-09-06)Live source ↗