The claim, verbatim

Applied Digital signed three new campuses totaling 810 MW of capacity (Polaris Forge 3, Delta Forge 2, and one additional) contracted to one investment-grade hyperscaler

Source (primary)

How Far Can Applied Digital Stock Fall If The Business Keeps Growing? - Trefis (-, news_article)
View cached copy (2026-09-18)Live source ↗

Quote: “Applied Digital signed three campuses in four months, among them Polaris Forge 3 and Delta Forge 2, all three to one investment-grade hyperscaler... The question that followed is whether the 810 megawatts in them went out at lower yields than peers get.”

How we checked this

Checked on September 24, 2026. The cited source supports every part of this claim.

The article names Polaris Forge 3 and Delta Forge 2 among three campuses signed to one investment-grade hyperscaler, and refers to the 810 megawatts in them.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.trefis.com/stock/apld/articles/615215/how-far-can-applied-digital-stock-fall-if-the-business-keeps-growing/2026-09-14) in full (11,065 characters, retrieved September 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms How Far Can Applied Digital Stock Fall If The Business Keeps Growing? - Trefis

Quote: “Applied Digital signed three campuses in four months, among them Polaris Forge 3 and Delta Forge 2, all three to one investment-grade hyperscaler... The question that followed is whether the 810 megawatts in them went out at lower yields than peers get.”

View cached copy (2026-09-18)Live source ↗