jain.com

100 MW HPC facility under construction in Ellendale

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2024-04-11
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

100 MW high-performance compute facility under construction in Ellendale, North Dakota

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota”

View cached copy (2026-09-01)Live source ↗Archive.org ↗