Polaris Forge 2

Project of Applied Digital

Kind
datacenter
Location
Harwood, North Dakota
County
Cass County
State/region
ND
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook200 MW IT load2026-09-01Investment Grade Hyperscaler Polaris Forge 2 lease
Under construction280 MW2025-12-04Polaris Forge 2 Construction and Capacity Timeline
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure1,000 MW2025-10-09Polaris Forge 2 - potential expansion to 1 GW

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-10-22
Undisclosed counterparty (one or more) - tenant · 200 MW · 15-year term source
2026-03-01
Oracle - tenant source

Claims about this project

2025-09-11 - stated
Polaris Forge 2 operational timeline. Promised by 2026-12-31.
2025-09-11 - stated
2025-09-11 - stated
Polaris Forge 2 investment 3000000000.0 USD.
2025-09-11 - delayed
200 MW Lease Execution deadline for Polaris Forge 2 200.0 MW. Promised by 2025-10-31.
2025-09-21 - stated
Polaris Forge 2 operational timeline. Promised by 2027-12-31.
2025-09-21 - stated
2025-09-21 - stated
2025-10-09 - stated
Polaris Forge 2 - initial 200 MW capacity timeline 200.0 MW. Promised by 2027-12-31.
2025-12-04 - stated
2025-12-04 - stated
2025-12-04 - stated
2026-01-07 - stated
2026-03-09 - stated
2026-03-12 - stated
2026-07-28 - delayed
Polaris Forge 2 groundbreaking 200.0 MW. Promised by 2025-08-18.
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - stated
Polaris Forge 2 capacity delivery timeline 200.0 MW. Promised by 2027-03-31.
2026-07-28 - delayed
Polaris Forge 2 customer lease 200.0 MW. Promised by 2025-10-22.
2026-07-28 - delayed
Investment-grade hyperscaler lease at Polaris Forge 2 5.0 billion USD. Promised by 2025-10-22.
2026-07-28 - stated
2026-08-22 - stated
2026-09-01 - stated
Polaris Forge 2 capacity milestones 200.0 MW. Promised by 2027-03-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 2 initial capacity timeline 200.0 MW. Promised by 2026-12-31.
2026-09-01 - stated
Polaris Forge 2 full capacity timeline 200.0 MW. Promised by 2027-03-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 2 full capacity date. Promised by 2027-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
$2.15B Senior Secured Notes due 2031 2.15 billion USD. Promised by 2031-01-01.
2026-09-01 - stated
$2.15 billion Senior Secured Notes offering 2150000000.0 USD. Promised by 2031-12-31.
2026-09-01 - stated
2026-09-01 - stated
Investment Grade Hyperscaler Polaris Forge 2 lease 200.0 MW. Promised by 2027-06-30.