Polaris Forge 2 groundbreaking and construction timeline

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility timeline
Statement date
2026-07-28
Promised by
2026-12-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Broke ground on Polaris Forge 2 data center campus near Harwood, North Dakota on August 18, 2025; anticipate reaching initial capacity in second half of 2026 and full capacity in early 2027

Source (primary)

Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “On August 18, 2025, we broke ground on our Polaris Forge 2 data center campus near Harwood, North Dakota...We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2026-07-29

Quote: “On August 18, 2025, we broke ground on our Polaris Forge 2 data center campus near Harwood, North Dakota...We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”