Polaris Forge 2 groundbreaking and construction timeline

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility timeline
Statement date
2026-07-28
Promised by
2026-12-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Broke ground on Polaris Forge 2 data center campus near Harwood, North Dakota on August 18, 2025; anticipate reaching initial capacity in second half of 2026 and full capacity in early 2027

Source (primary)

Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “On August 18, 2025, we broke ground on our Polaris Forge 2 data center campus near Harwood, North Dakota...We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”

How we checked this

Checked on September 13, 2026. The cited source supports every part of this claim.

The 10-K gives the August 18, 2025 groundbreaking near Harwood and the expected initial and full capacity timing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000048/apld-20260531.htm) in full (594,188 characters, retrieved August 30, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2026-07-29

Quote: “On August 18, 2025, we broke ground on our Polaris Forge 2 data center campus near Harwood, North Dakota...We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”