jain.com

Data center leases executed in North Dakota

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility timeline
Statement date
2026-01-15
Current status
stated

The claim, verbatim

The Company has negotiated and executed leases for data center campuses named Polaris Forge 1 and Polaris Forge 2 in North Dakota

Source (primary)

Applied Digital 8-K filed 2026-01-16 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “the negotiation and execution of the leases for the Company's data center campuses in North Dakota (Polaris Forge 1 and Polaris Forge 2)”

How we checked this

Attempted on September 16, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315226002580/form8-k.htm) in full (6,217 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 8-K filed 2026-01-16

Quote: “the negotiation and execution of the leases for the Company's data center campuses in North Dakota (Polaris Forge 1 and Polaris Forge 2)”

View cached copy (2026-08-31)Live source ↗