Harwood both buildings expected complete in 2028
Company: Applied Digital - Project: Polaris Forge 2
The claim, verbatim
Both Harwood data center buildings are expected to be completed in 2028, when projected annual property tax collections for Fargo Public Schools reach about $4.36 million, per the mayor's projections.
Source (primary)
Harwood mayor reveals millions in projected tax revenue for Fargo Public Schools from Applied Digital data center - Valley News Live (-, news_article)
View cached copy (2026-11-08)Live source ↗Archive.org ↗
Quote: “projected annual property tax collections beginning in 2028, when both buildings are expected to be completed”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The mayor's projections in the article put Fargo Public Schools' annual tax revenue at $4,358,410.56 starting in 2028, when both buildings are expected to be complete.
Confirmed in the source:
- Both Harwood data center buildings are expected to be completed in 2028
- Projected annual property tax collections for Fargo Public Schools are about $4.36 million ($4,358,410.56) in 2028
- These figures are the mayor's projections
What we did: Read our cached copy of the publisher (https://www.valleynewslive.com/2026/11/07/harwood-mayor-reveals-millions-projected-tax-revenue-fargo-public-schools-applied-digital-data-center/) in full (20,358 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Harwood mayor reveals millions in projected tax revenue for Fargo Public Schools from Applied Digital data center - Valley News Live
Quote: “projected annual property tax collections beginning in 2028, when both buildings are expected to be completed”