Polaris Forge 2 capacity delivery timeline
Company: Applied Digital - Project: Polaris Forge 2
The claim, verbatim
Applied Digital anticipates Polaris Forge 2 reaching initial capacity in the second half of 2026 and full capacity in early 2027.
Source (primary)
Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗
Quote: “We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 10-K filed 2026-07-29
Quote: “We currently anticipate reaching initial capacity in the second half of calendar year 2026 and full capacity in early calendar year 2027.”