Approximately 15-year lease agreement with U.S. based investment grade hyperscaler for 200 MW critical IT load at Polaris Forge 2
Source (primary)
Applied Digital S-3 filed 2025-12-05 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “On October 22, 2025, we announced that we entered into an approximately 15-year lease agreement with a U.S. based investment grade hyperscaler for 200 MW of critical IT load at our Polaris Forge 2 campus”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The prospectus states the announcement date, the approximately 15-year term, the counterparty description, and the 200 MW of critical IT load at Polaris Forge 2.
Confirmed in the source:
- Applied Digital announced on October 22, 2025 a lease with a U.S. based investment grade hyperscaler
- The lease term is approximately 15 years
- The lease covers 200 MW of critical IT load at the Polaris Forge 2 campus
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315225026369/forms-3.htm) in full (89,712 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-3 filed 2025-12-05
Quote: “On October 22, 2025, we announced that we entered into an approximately 15-year lease agreement with a U.S. based investment grade hyperscaler for 200 MW of critical IT load at our Polaris Forge 2 campus”