Polaris Forge 2 full capacity delivery

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-09-25
Promised by
2027-03-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 2 campus full capacity of 200 MW expected to come online by early calendar 2027

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “with full capacity online by early calendar 2027”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “with full capacity online by early calendar 2027”