Polaris Forge 2 data center capacity and lease

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility capacity
Statement date
2026-02-08
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 2 is a 200MW data center campus in Harwood, North Dakota with signed lease for 200MW to an investment-grade hyperscaler tenant and in early construction phases

Source (primary)

Applied Digital 8-K filed 2026-02-09 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “signing a lease for 200MW of its Harwood, North Dakota campus ("Polaris Forge 2"), which is in early construction phases, with an investment-grade hyperscaler tenant”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 8-K filed 2026-02-09

Quote: “signing a lease for 200MW of its Harwood, North Dakota campus ("Polaris Forge 2"), which is in early construction phases, with an investment-grade hyperscaler tenant”