Advanced lease talks with investment-grade hyperscaler for Polaris Forge 2

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
customer
Statement date
2025-10-09
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

In advanced discussions with an investment-grade hyperscaler, aligned on many key lease terms; customer would hold right of first refusal on full 1 GW; initial 200 MW would bring total leased capacity to 600 MW.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “We are currently in advanced discussions with an investment-grade hyperscaler and have aligned on many of the key lease terms with them.”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The press release's management commentary on Polaris Forge 2 states each element: the advanced talks, the aligned terms, the conditional right of first refusal on 1 GW, and the 600 MW total leased capacity once the initial 200 MW is signed.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/131/applied-digital-reports-fiscal-first-quarter-2026-results/) in full (34,802 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “We are currently in advanced discussions with an investment-grade hyperscaler and have aligned on many of the key lease terms with them.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-10-09.