In advanced discussions with an investment-grade hyperscaler for Polaris Forge 2, aligned on many key lease terms; the customer would hold a right of first refusal on the full 1 GW, and the initial 200 MW would bring total leased capacity to 600 MW.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗
Quote: “We are currently in advanced discussions with an investment-grade hyperscaler and have aligned on many of the key lease terms with them.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states each element, presenting the right of first refusal and the 600 MW total as conditional on the lease being signed.
Confirmed in the source:
- Applied Digital is in advanced discussions with an investment-grade hyperscaler for Polaris Forge 2
- The parties have aligned on many key lease terms
- If the lease is executed, the customer would hold a right of first refusal on the full 1 GW, contingent on securing additional power
- The initial 200 MW would bring total leased capacity to 600 MW
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/131/applied-digital-reports-fiscal-first-quarter-2026-results/) in full (34,802 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “We are currently in advanced discussions with an investment-grade hyperscaler and have aligned on many of the key lease terms with them.”
confirms Earnings Release
Quote: “We are currently in advanced discussions with an investment-grade hyperscaler and have aligned on many of the key lease terms with them.”