Polaris Forge 2 200MW AI Factory campus in Harwood, North Dakota

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility capacity
Statement date
2026-03-03
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

200 megawatts of critical IT load at Polaris Forge 2 AI Factory campus in Harwood, North Dakota to be funded by net proceeds of the $2.15 billion note offering

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗

Quote: “APLD Compute 2 intends to use the net proceeds from the Offering to fund the development and construction of 200 megawatts of critical IT load at Polaris Forge 2, its AI Factory campus in Harwood, North Dakota”

How we checked this

Checked on September 20, 2026. The cited source supports every part of this claim.

The document explicitly states net proceeds will fund 200 MW of critical IT load at Polaris Forge 2, its AI Factory campus in Harwood, North Dakota.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315226008772/ex99-1.htm) in full (8,181 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “APLD Compute 2 intends to use the net proceeds from the Offering to fund the development and construction of 200 megawatts of critical IT load at Polaris Forge 2, its AI Factory campus in Harwood, North Dakota”

View cached copy (2026-09-13)Live source ↗