Polaris Forge 2 construction and capacity timeline

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
facility timeline
Statement date
2026-04-07
Promised by
2027-03-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Applied Digital broke ground on Polaris Forge 2, a $3 billion 200 MW data center campus near Harwood, North Dakota on August 18, 2025, with initial capacity anticipated in calendar 2026 and full capacity online by early 2027.

Source (primary)

applied-digital 8-K exhibit (apldq326earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-10)Live source ↗

Quote: “On August 18, 2025, we broke ground on Polaris Forge 2, a $3 billion, 200 MW data center campus near Harwood, North Dakota. Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027.”

How we checked this

Checked on September 20, 2026. The cited source supports every part of this claim.

All details of the Polaris Forge 2 timeline and description appear in the source.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000029/apldq326earningsrelease.htm) in full (46,258 characters, retrieved September 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apldq326earningsrelease.htm)

Quote: “On August 18, 2025, we broke ground on Polaris Forge 2, a $3 billion, 200 MW data center campus near Harwood, North Dakota. Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027.”

View cached copy (2026-09-10)Live source ↗