jain.com

Investment Grade Hyperscaler Polaris Forge 2 lease

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
customer
Statement date
2026-09-01
Promised by
2027-06-30
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Applied Digital signed two 15-year leases with two 5-year renewal options for 2 buildings at Polaris Forge 2 with a U.S. based Investment-Grade Hyperscaler, utilizing 200 MW of Critical IT load.

Source (primary)

Investor Presentation (IR page (ir.applieddigital.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “U.S. Based Investment-Grade Hyperscaler - Signed two 15-year leases with two 5- year options for 2 buildings at Polaris Forge 2, utilizing 200 MW of Critical IT load”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Investor Presentation

Quote: “U.S. Based Investment-Grade Hyperscaler - Signed two 15-year leases with two 5- year options for 2 buildings at Polaris Forge 2, utilizing 200 MW of Critical IT load”

View cached copy (2026-09-01)Live source ↗Archive.org ↗