Investment-grade hyperscaler 200 MW lease at Polaris Forge 2
Company: Applied Digital - Project: Polaris Forge 2
The claim, verbatim
Applied Digital signed an approximately 15-year lease with a U.S.-based investment-grade hyperscaler for 200 MW at Polaris Forge 2 on October 22, 2025.
Source (primary)
applied-digital 8-K exhibit (apldq326earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-10)Live source ↗
Quote: “On October 22, 2025, we signed an approximately 15-year lease with a U.S. based investment-grade hyperscaler for 200 MW at Polaris Forge 2.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (apldq326earningsrelease.htm)
Quote: “On October 22, 2025, we signed an approximately 15-year lease with a U.S. based investment-grade hyperscaler for 200 MW at Polaris Forge 2.”