Polaris Forge 2 full 200 MW capacity
Company: Applied Digital - Project: Polaris Forge 2
The claim, verbatim
Full 200 MW capacity at Polaris Forge 2 expected to be online by early calendar 2027
Source (primary)
applied-digital 8-K exhibit (apldq226earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-22)Live source ↗
Quote: “Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027”
How we checked this
Checked on September 26, 2026. The cited source supports every part of this claim.
The release describes Polaris Forge 2 as a 200 MW campus. It says full capacity is expected online by early calendar 2027.
Confirmed in the source:
- Polaris Forge 2 is a 200 MW campus
- Full capacity at Polaris Forge 2 is expected online by early calendar 2027
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000002/apldq226earningsrelease.htm) in full (44,381 characters, retrieved September 22, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027”