jain.com

$2.15B 6.750% Senior Secured Notes due 2031

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
financing
Statement date
2026-04-08
Promised by
2031-12-31
Promised amount
2150000000.0 USD
Current status
stated

The claim, verbatim

Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par via APLD ComputeCo 2 LLC, to fund construction of 200 MW at Polaris Forge 2 in Harwood, ND.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par through its subsidiary APLD ComputeCo 2 LLC. Proceeds will fund the development and construction of 200 MW of critical IT load at the Polaris Forge 2 AI Factory campus”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release confirms the notes' amount, coupon, maturity, issue price, issuing subsidiary, and use of proceeds for 200 MW at Polaris Forge 2 in Harwood, ND.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/148/applied-digital-reports-fiscal-third-quarter-2026-results/) in full (47,470 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par through its subsidiary APLD ComputeCo 2 LLC. Proceeds will fund the development and construction of 200 MW of critical IT load at the Polaris Forge 2 AI Factory campus”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par through its subsidiary APLD ComputeCo 2 LLC. Proceeds will fund the development and construction of 200 MW of critical IT load at the Polaris Forge 2 AI Factory campus in Harwood, North Dakota.”

View cached copy (2026-10-03)Live source ↗

confirms Earnings Release

Quote: “Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par through its subsidiary APLD ComputeCo 2 LLC.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Completed a $2.15 billion private offering of 6.750% Senior Secured Notes due 2031, issued at 98% of par through its subsidiary APLD ComputeCo 2 LLC. Proceeds will fund the development and construction of 200 MW of critical IT load at the Polaris Forge 2 AI Factory campus in Harwood, North Dakota.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2026-04-08.