Jamestown

Project of Applied Digital

Kind
campus
Location
2671 Highway 20 SE, Jamestown, ND
County
Stutsman County
State/region
ND
Country
US
Status
operational as of October 7, 2026

Where it stands

Applied Digital's 106 MW Jamestown, ND crypto-mining hosting facility (JMS01) was operating at full capacity as of August 31, 2026, per the Q1 FY2027 earnings release and 10-Q. The July 2026 10-K describes the hosting business as a legacy line serving a single crypto customer with about 1.5 years remaining on its contract, and the Jamestown energy services commitment had about 0.4 years left as of August 31, 2026. A separate 9 MW HPC/cloud data center in Jamestown is mentioned in investor timelines, but it is not counted here because no passage ties it to this facility's capacity.

106 MW in service

PhaseMWStatusDateSource
Jamestown blockchain hosting facility (JMS01)106operational2026-08-31As of August 31, 2026, the Company’s 106 MW facility in Jamestown, ND, and 180 MW facility in Ellendale, ND, were operating at full capacity.
2026-10-07 View cached copy (2026-10-08)Live source ↗Archive.org ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 7, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today106 MW2026-10-15Jamestown facility capacity
Contracted a customer is on the hook309.6 MW2023-05-16Marathon Digital Holdings hosting contract
Under construction100 MW2026-10-06Jamestown ND facility capacity
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure106 MW2026-09-17Jamestown facility capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2021-11-01
GMR - tenant · 50 MW source
replaced on 2023-05-15 inferred
Marathon Digital Holdings committed 309.60 MW on 2023-05-15, taking live commitments at this site to 359.6 MW against a best-known capacity of 309.6 MW. No termination was announced for GMR; the site cannot carry both, so we record the earlier commitment as replaced.
2022-03-20
JointHash Holding Limited - tenant source
2022-03-20
Bitmain Technologies Limited - tenant source
2022-03-20
Hashing LLC - tenant source
2022-03-20
F2Pool Mining Inc. - tenant source
2022-08-28
Spring Mud - tenant source
2023-05-15
Marathon Digital Holdings, Inc. - offtaker · 309.6 MW · 5-year term source
replaced on 2023-05-15 inferred
GMR committed 50.00 MW on 2023-05-15, taking live commitments at this site to 359.6 MW against a best-known capacity of 309.6 MW. No termination was announced for Marathon Digital Holdings; the site cannot carry both, so we record the earlier commitment as replaced.
2023-05-16
Foundry Technologies - jv partner source

Claims about this project

2021-11-01 - stated
2021-11-01 - stated
2021-11-01 - verified
2021-11-01 - stated
2021-11-21 - stated
2021-11-21 - stated
2021-11-21 - verified
First co-hosting facility completion. Promised by 2021-12-31.
2021-11-30 - verified
2021-11-30 - stated
2021-11-30 - stated
2021-11-30 - outcome unconfirmed
2022-03-20 - stated
2022-03-20 - stated
2022-03-20 - stated
2022-03-20 - verified
First facility 45MW expansion online 45.0 MW. Promised by 2022-06-30.
2022-03-27 - stated
2022-03-27 - stated
2022-03-27 - verified
First facility 45MW phase online by Q2 2022 45.0 MW. Promised by 2022-06-30.
2022-04-07 - verified
First facility 45MW remaining capacity 45.0 MW. Promised by 2022-06-30.
2022-04-07 - stated
2022-04-07 - stated
2022-04-07 - stated
2022-04-11 - stated
2022-04-11 - verified
First facility remaining capacity deployment 45.0 MW. Promised by 2022-06-30.
2022-04-11 - stated
2022-04-11 - stated
2022-04-12 - stated
2022-04-12 - verified
2022-04-12 - verified
North Dakota facility 45MW expected Q2 2022 45.0 MW. Promised by 2022-06-30.
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-05-13 - stated
2022-07-17 - verified
2022-07-17 - verified
2022-08-11 - stated
Loan advance schedule 3000000.0 USD.
2022-08-25 - stated
2022-08-25 - stated
2022-09-08 - stated
2022-09-08 - stated
2022-09-15 - stated
2022-09-15 - stated
2022-09-15 - stated
2022-09-26 - stated
2022-10-11 - stated
2022-10-11 - stated
2023-01-09 - verified
5MW specialized processing center energization 5.0 MW. Promised by 2023-03-31.
2023-01-09 - verified
2023-01-09 - stated
2023-01-09 - stated
2023-01-09 - verified
2023-01-09 - stated
2023-01-09 - stated
2023-01-09 - stated
2023-04-06 - verified
2023-04-06 - stated
2023-04-06 - verified
2023-04-06 - delayed
HPC facility full capacity completion. Promised by 2023-12-31.
2023-04-06 - stated
2023-04-06 - stated
2023-04-06 - stated
2023-04-06 - stated
2023-04-06 - outcome unconfirmed
Jamestown HPC full capacity by year-end 5.0 MW. Promised by 2023-12-31.
2023-05-15 - stated
2023-05-15 - stated
2023-05-15 - stated
2023-05-15 - stated
2023-05-15 - stated
2023-05-15 - stated
2023-05-15 - stated
2023-05-16 - stated
2023-05-16 - stated
2023-05-16 - stated
2023-05-16 - stated
2023-05-16 - stated
2023-06-25 - delayed
Jamestown HPC facility online date 9.0 MW. Promised by 2023-12-31.
2023-06-25 - stated
2023-06-25 - delayed
Jamestown HPC facility expansion to 9 MW 9.0 MW. Promised by 2023-12-31.
2023-06-25 - delayed
2023-07-24 - stated
2023-08-01 - delayed
2023-08-01 - delayed
HPC facility in Jamestown, North Dakota 9.0 MW. Promised by 2023-12-31.
2023-08-01 - stated
2024-01-16 - stated
2024-04-11 - stated
2024-05-16 - stated
2024-05-16 - stated
2024-05-30 - stated
2024-05-30 - stated
2024-06-16 - stated
2024-06-16 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-09-10 - stated
2024-09-12 - stated
2024-09-12 - stated
2024-09-22 - stated
2024-10-03 - stated
2024-10-03 - stated
2024-10-17 - stated
2024-10-21 - stated
2024-10-22 - stated
2024-10-22 - stated
2025-04-13 - stated
2025-07-29 - stated
2025-12-04 - stated
2026-07-28 - stated
2026-09-17 - stated
2026-09-17 - stated
2026-09-21 - stated
2026-09-23 - stated
2026-10-08 - stated
2026-10-15 - stated

Site intelligence

Analytical estimate. Each site below is located from public records (filings, releases, news, OpenStreetMap) and checked against free satellite imagery; "How we located this site" lists every step and the score it earned. The conclusion is computed from night-time lights, surface heat and year-over-year change, with the dates it rests on. These are hypotheses under active tracking, not legal parcels or an official endorsement.
2671 STATE HWY 20, JAMESTOWN, ND, 58401
Candidate
Stutsman County, ND
47.0296, -98.6791
Approximate address 2651 ND-20, Jamestown, ND 58401, USA Reverse-geocoded from the candidate centroid; not a permit-confirmed parcel address.
Conclusion so far Something is built here, but no sign yet that it is running. · confidence 30%
Undetermined -- a built footprint is visible but neither lights nor heat show activity: night-time lights at the site ran 0.16x the surrounding area (0 of 3 clear nights, 2026-09-22 to 2026-10-04); surface temperature -0.5 K against its surroundings (2 pass(es), 2026-10-10 to 2026-10-17). Based on 14 clear observation(s) from 2026-06-21 to 2026-10-19.
What would change this: Night-time lights or a heat signature at the footprint.
Latest clear imagery: Google 2026-10-18 · ECOSTRESS thermal 2026-10-17 · Sentinel-2 2026-10-16 · radar 2026-10-13 · Landsat 2026-10-10 · night lights 2026-10-04 · NAIP 2023-07-02
Newest clear images145 clear image date(s)
Visual view of applied-digital-jamestown, 2026-10-18 (Google Earth (wide view))
2026-10-18Google Earth (wide view) · 3.26 m/pixel
Visual view of applied-digital-jamestown, 2026-10-18 (Google Earth (close view))
2026-10-18Google Earth (close view) · 0.41 m/pixel
Thermal view of applied-digital-jamestown, 2026-10-17 (ECOSTRESS thermal)
2026-10-17ECOSTRESS thermal · 70 m/pixel
Visual view of applied-digital-jamestown, 2026-10-16 (Sentinel-2)
2026-10-16Sentinel-2 · 10 m/pixel
How we located this site
35/100 (candidate): street location 25 + 1 independent source family 10
  1. Starting point (the project's stated locality) 2026-10-19
    2671 Highway 20 SE, Jamestown, ND → 47.02959, -98.67909 (street)
  2. Located from a published address 2026-10-19
    2671 Highway 20 SE, Jamestown, ND → 47.02959, -98.67909 (street)
  3. OpenStreetMap features nearby 2026-10-19
    0 named match(es)
Recent changes
  • 2026-10-13 vs 2026-10-01: structural change (radar signal shift) — Sentinel-1 backscatter decreased over the 11-day interval, with VV down 3.2 dB and VH down 1.2 dB, consistent with a structural change such as reduced double-bounce or surface-scattering returns at the site.
  • 2026-10-01 vs 2026-09-12: structural change (radar signal shift) — Sentinel-1 backscatter increased by +4.0 dB in VV and +2.9 dB in VH over the 18-day interval, consistent with new or altered structural elements visible at the site.
  • 2026-10-01 vs 2026-09-21: clearing or grading visible — Over the 10-day interval between Sentinel-2 scenes, NDVI decreased by 0.172 while NDBI increased by 0.166, a pattern consistent with vegetation removal and exposed soil or graded surfaces at the site.
  • 2026-10-06 vs 2026-10-01: structural change (radar signal shift) — Sentinel-1 backscatter decreased in both VH (−4.58 dB) and VV (−4.18 dB) over the 5-day interval, consistent with a reduction in structural or surface scattering at the site.
  • 2025-06-17 vs 2025-06-01: vegetation recovery visible

Satellite imagery on this page is drawn from the Google Earth satellite basemap, USDA NAIP aerial photography (~1 m/pixel), ESA Sentinel-2 multispectral (10 m, with per-date cloud masks), NASA / USGS Landsat 8/9 (30 m, plus surface temperature), ESA Sentinel-1 radar (all-weather, night), NASA ECOSTRESS thermal (~70 m), and NASA Black Marble night lights (500 m, daily). Each image is dated, labelled by source and pixel resolution, and downloadable at its native size; cloudy dates are kept and marked rather than hidden. New scenes are pulled daily as each provider publishes them.