HPC facility full capacity completion
Company: Applied Digital - Project: Jamestown
What the later record shows
The date slipped
Only an initial 200 kW stage was energized in 2023. The facility was still described as 'nearing completion' in October 2024 and January 2025, so full capacity missed year-end 2023.
“successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”
2024-10-21 · ARS View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
HPC facility will be completed in two additional stages with full capacity online by year end
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “The facility will be completed in two additional stages with full capacity online by year end”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release states that the HPC facility would be completed in two additional stages with full capacity online by year end. This was a plan stated in April 2023.
Confirmed in the source:
- The new HPC facility will be completed in two additional stages
- Full capacity was expected online by year end
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,328 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end”
delays ARS
Quote: “The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”
delays Earnings Release
Quote: “successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”