HPC facility full capacity completion

Company: Applied Digital - Project: Jamestown

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2023-04-06
Promised by
2023-12-31
Current status
delayed

What the later record shows

The date slipped

Only an initial 200 kW stage was energized in 2023. The facility was still described as 'nearing completion' in October 2024 and January 2025, so full capacity missed year-end 2023.

“successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”
2024-10-21 · ARS View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

HPC facility will be completed in two additional stages with full capacity online by year end

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The facility will be completed in two additional stages with full capacity online by year end”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release states that the HPC facility would be completed in two additional stages with full capacity online by year end. This was a plan stated in April 2023.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,328 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The facility will be completed in two additional stages with full capacity online by year end”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays ARS

Quote: “The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays Earnings Release

Quote: “successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2023-04-06.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.