GPU processing facility construction
Company: Applied Digital - Project: Jamestown
What the later record shows
Not a promise: a reported event · happened December 14, 2022
The claim reports that construction began on December 14, 2022, which had already happened when it was said. Later filings repeat the date.
“On December 14, 2022, the Company began construction of its latest specialized processing center, a 5 MW facility next to the Company’s currently operating 100-MW hosting facility in Jamestown, North Dakota.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Began construction on December 14, 2022 of 5 MW GPU processing facility at Jamestown
Source (primary)
Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “On December 14, 2022, the Company began construction of its latest specialized processing center, a 5 MW facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states the construction start date, the 5 MW size, the Jamestown location, and the GPU-specific design.
Confirmed in the source:
- On December 14, 2022, Applied Digital began construction of a 5 MW specialized processing facility
- The facility is next to the company's 100 MW hosting facility in Jamestown, North Dakota
- The building is designed and purpose-built for GPUs
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000135/apld-424b3finalprospectus0.htm) in full (53,674 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B3 filed 2023-05-16
Quote: “On December 14, 2022, the Company began construction of its latest specialized processing center, a 5 MW facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota.”