HPC facility capacity in Jamestown
Company: Applied Digital - Project: Jamestown
The claim, verbatim
9 MW capacity for GPU-based high-performance computing facility
Source (primary)
Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We subsequently determined to increase the capacity of this facility to 9 MW”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 424B5 filed 2023-06-26
Quote: “We subsequently determined to increase the capacity of this facility to 9 MW”