HPC facility capacity in Jamestown
Company: Applied Digital - Project: Jamestown
The claim, verbatim
9 MW capacity for GPU-based high-performance computing facility
Source (primary)
Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We subsequently determined to increase the capacity of this facility to 9 MW”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states the facility capacity was increased to 9 MW and is purpose-built for GPUs.
Confirmed in the source:
- The Jamestown HPC facility capacity was increased to 9 MW
- The facility is purpose-built for GPU-based high-performance computing
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000166/apld-preliminaryprospectus.htm) in full (176,255 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B5 filed 2023-06-26
Quote: “We subsequently determined to increase the capacity of this facility to 9 MW”