First co-hosting facility completion
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered late · happened February 2, 2022
The North Dakota facility promised for Q4 2021 came online on February 2, 2022, which is after the target.
“If not already online, install customer equipment and bring online our first facility in Jamestown, ND.”
2022-01-05 · Applied Digital S-1/A filed 2022-01-06 View cached copy (2026-09-13)Live source ↗
“On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
First co-hosting facility in North Dakota; installation began October 2021; expected completion Q4 2021
Source (primary)
Applied Digital S-1 filed 2021-11-22 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing says the company bought property in North Dakota for its first co-hosting facility, that installation began in October 2021, and that it expected completion in Q4 2021.
Confirmed in the source:
- The company's first co-hosting facility is located on property it purchased in North Dakota
- Installation of the first co-hosting facility began in October 2021
- The company expected the first co-hosting facility to be completed in the fourth quarter of calendar year 2021
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465921142627/tm2132377-8_s1.htm) in full (515,456 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1 filed 2021-11-22
Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”
confirms Applied Digital 10-K filed 2023-08-02
Quote: “On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”
confirms Applied Digital S-1/A filed 2022-01-06
Quote: “If not already online, install customer equipment and bring online our first facility in Jamestown, ND.”