First co-hosting facility completion

Company: Applied Digital - Project: Jamestown

Subject kind
facility timeline
Statement date
2021-11-21
Promised by
2021-12-31
Current status
verified

What the later record shows

Delivered late · happened February 2, 2022

The North Dakota facility promised for Q4 2021 came online on February 2, 2022, which is after the target.

“If not already online, install customer equipment and bring online our first facility in Jamestown, ND.”
2022-01-05 · Applied Digital S-1/A filed 2022-01-06 View cached copy (2026-09-13)Live source ↗
“On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

First co-hosting facility in North Dakota; installation began October 2021; expected completion Q4 2021

Source (primary)

Applied Digital S-1 filed 2021-11-22 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing says the company bought property in North Dakota for its first co-hosting facility, that installation began in October 2021, and that it expected completion in Q4 2021.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465921142627/tm2132377-8_s1.htm) in full (515,456 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1 filed 2021-11-22

Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-K filed 2023-08-02

Quote: “On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital S-1/A filed 2022-01-06

Quote: “If not already online, install customer equipment and bring online our first facility in Jamestown, ND.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.