Jamestown GPU facility
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Company constructed 9 MW separate GPU facility in Jamestown, North Dakota in 2023 for HPC workloads
Source (primary)
Applied Digital S-1 filed 2024-05-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “In 2023, we constructed a separate and unique building, designed and purpose-built for GPUs, which is separate from our crypto hosting buildings, next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota, with a total capacity of 9 MW.”
How we checked this
Checked on September 18, 2026. The cited source supports every part of this claim.
The filing describes a 9 MW GPU-dedicated building constructed in Jamestown in 2023. It separately says the company has 9 MW of HPC hosting capacity at that location.
Confirmed in the source:
- In 2023, Applied Digital constructed a separate building purpose-built for GPUs in Jamestown, North Dakota
- The building has a total capacity of 9 MW
- The GPU capacity supports high-performance computing workloads, including AI
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000143/yorkvilles-1.htm) in full (115,497 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1 filed 2024-05-31
Quote: “In 2023, we constructed a separate and unique building, designed and purpose-built for GPUs, which is separate from our crypto hosting buildings, next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota, with a total capacity of 9 MW.”