Jamestown 5MW HPC processing center energization Q1 2023
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered late
The Q1 2023 energization target was missed: as of April 6, 2023, it was still 4-5 weeks out. Initial capacity at the adjacent Jamestown HPC facility was reported energized by July 24, 2023.
“We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”
2023-04-06 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
A new 5MW specialized processing center in Jamestown, broken ground December 14, 2022, is planned for energization in Q1 calendar 2023 to host an HPC machine learning customer.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application.”
How we checked this
Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.
The release supports the 5MW Jamestown center, its Q1 2023 energization target and the machine learning customer. However, December 14, 2022 is given as the date the groundbreaking was announced, not necessarily the date ground was broken.
Confirmed in the source:
- A new 5MW specialized processing center is being built in Jamestown, North Dakota, adjacent to the existing 100MW facility
- The 5MW building is planned for energization in the first calendar quarter of 2023
- The 5MW building will host a new HPC customer for a machine learning application
- Applied Digital announced groundbreaking of the 5MW center on December 14, 2022
We could not confirm this from the cited source:
- That ground was actually broken on December 14, 2022 (the release gives that as the date the groundbreaking was announced)
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (26,009 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application.”
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application.”
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application.”
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application.”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
confirms Earnings Release
Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”