GMR hosting services contract
Company: Applied Digital - Project: Jamestown
The claim, verbatim
GMR signed contract for approximately 50MW of capacity (50% of 100MW) at the first facility
Source (primary)
Applied Digital S-1/A filed 2022-03-21 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “GMR has also been a proponent of our hosting strategy, having signed a contract for approximately 50% of our 100MW capacity as part of our hosting operation under development”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document states GMR signed a contract for approximately 50% of the 100MW capacity, which equals about 50MW.
Confirmed in the source:
- GMR signed a contract for approximately 50% of the company's 100MW capacity, equivalent to roughly 50MW, at the first facility
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922036163/tm2124821-21_s1a.htm) in full (555,375 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2022-03-21
Quote: “GMR has also been a proponent of our hosting strategy, having signed a contract for approximately 50% of our 100MW capacity as part of our hosting operation under development”