Jamestown HPC full capacity by year-end
Company: Applied Digital - Project: Jamestown
What the later record shows
The date slipped
Full capacity was not online by year-end 2023. In October 2024 the company still said the Jamestown HPC facility was 'nearing completion'.
“The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”
2024-10-21 · ARS View cached copy (2026-09-01)Live source ↗Archive.org ↗
“The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”
2025-01-13 · Applied Digital 10-Q filed 2025-01-14 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Jamestown HPC facility full 5-MW capacity expected online by year-end 2023
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “The facility will be completed in two additional stages with full capacity online by year end”
How we checked this
Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.
The release gives the 5 MW size and a 'by year end' target, but does not specify that this means calendar year-end 2023.
Confirmed in the source:
- The Jamestown HPC facility is a 5 MW standalone processing center
- Full capacity of the HPC facility is expected online by year end
We could not confirm this from the cited source:
- That the 'year end' referred to is calendar year-end 2023 (the release says only 'by year end', and the company's fiscal year ends May 31)
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end”
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end.”
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end.”
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end.”
confirms Earnings Release
Quote: “The facility will be completed in two additional stages with full capacity online by year end.”
delays ARS
Quote: “The Company is currently building two HPC focused data centers. The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown”
delays Applied Digital 10-Q filed 2025-01-14
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”