First co-hosting facility completion expected Q4 2021
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered late · happened February 2, 2022
Completion was promised for Q4 2021, but the facility was brought online on February 2, 2022, after that date.
“We brought our first facility in Jamestown, ND online as to the first 55MW on February 2, 2022.”
2022-03-20 · Applied Digital S-1/A filed 2022-03-21 View cached copy (2026-09-13)Live source ↗
“On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Installation of first co-hosting facility began October 2021; facility expected to be completed in fourth quarter 2021
Source (primary)
Applied Digital S-1/A filed 2021-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing states both that installation began in October 2021 and that completion was expected in the fourth quarter of calendar 2021.
Confirmed in the source:
- Installation of the first co-hosting facility began in October 2021
- The company expected the facility to be completed in the fourth quarter of calendar year 2021
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465921145539/tm2124821-5_s1a.htm) in full (502,304 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2021-12-01
Quote: “Installation of our first co-hosting facility began in October 2021. We expect this facility to be completed in the fourth quarter of calendar year 2021.”
confirms Applied Digital 10-K filed 2023-08-02
Quote: “On February 2, 2022, we brought our first facility online and it has been fully operational since that date.”
confirms Applied Digital S-1/A filed 2022-03-21
Quote: “We brought our first facility in Jamestown, ND online as to the first 55MW on February 2, 2022.”