Jamestown HPC facility expansion to 9MW
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Applied Digital expanded the capacity of its specialized HPC datacenter adjacent to its existing 100MW Jamestown facility to 9MW and successfully energized initial capacity.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The HPC Update section of the release states this almost word for word.
Confirmed in the source:
- Applied Digital expanded its specialized HPC datacenter to 9MW
- The HPC datacenter is adjacent to its existing 100MW Jamestown facility
- Applied Digital successfully energized initial capacity at the HPC facility
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/66/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (23,127 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
confirms Earnings Release
Quote: “expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”