5 megawatt processing center energization

Company: Applied Digital - Project: Jamestown

Subject kind
facility timeline
Statement date
2023-01-09
Promised by
2023-03-31
Current status
verified

What the later record shows

Delivered late

Energization had not happened by April 6, 2023, when it was still expected in 4-5 weeks. Initial capacity was reported energized in the July 24, 2023 release.

“We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”
2023-04-06 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

5 megawatt processing center planned for energization in first calendar quarter of 2023

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The new building, planned for energization in the first calendar quarter of 2023”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release says the new building is planned for energization in the first calendar quarter of 2023.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (25,971 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The new building, planned for energization in the first calendar quarter of 2023”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2023-01-09.
October 9, 2026 — verified