5 megawatt processing center energization
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered late
Energization had not happened by April 6, 2023, when it was still expected in 4-5 weeks. Initial capacity was reported energized in the July 24, 2023 release.
“We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”
2023-04-06 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
5 megawatt processing center planned for energization in first calendar quarter of 2023
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “The new building, planned for energization in the first calendar quarter of 2023”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release says the new building is planned for energization in the first calendar quarter of 2023.
Confirmed in the source:
- The 5MW processing center was planned for energization in the first calendar quarter of 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (25,971 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
confirms Earnings Release
Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”