100 MW hosting capacity at Jamestown, North Dakota
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Amended and Restated Energy Services Agreement provides for 100 megawatts of electricity supply to co-hosting customers at Jamestown facility
Source (primary)
Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We entered into an Amended and Restated Energy Services Agreement for the purpose of supplying 100 megawatts ('MW') of electricity to be used by our co-hosting customers at this facility.”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states the agreement supplies 100 MW at the first North Dakota co-hosting facility, identified elsewhere as Jamestown.
Confirmed in the source:
- The Amended and Restated Energy Services Agreement supplies 100 MW of electricity to co-hosting customers at the North Dakota (Jamestown) facility
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000134/apld-424b3finalprospectus0.htm) in full (53,370 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B3 filed 2023-05-16
Quote: “We entered into an Amended and Restated Energy Services Agreement for the purpose of supplying 100 megawatts ('MW') of electricity to be used by our co-hosting customers at this facility.”