jain.com

Jamestown HPC facility expected online date

Company: Applied Digital - Project: Jamestown

Subject kind
facility timeline
Statement date
2023-08-01
Current status
stated

The claim, verbatim

GPU-optimized HPC facility in Jamestown expected to be brought online in second half of 2023

Source (primary)

Applied Digital 10-K filed 2023-08-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “This facility is expected to be brought online in the second half of calendar year 2023.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2023-08-02

Quote: “This facility is expected to be brought online in the second half of calendar year 2023.”

View cached copy (2026-09-13)Live source ↗