jain.com

Jamestown 106 MW facility fully operational

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2024-01-15
Promised amount
106.0 MW
Current status
stated

The claim, verbatim

As of November 30, 2023, the company's 106 MW facility in Jamestown, North Dakota was fully operational.

Source (primary)

applied-digital 8-K exhibit (apld2q24earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-14)Live source ↗

Quote: “the Company's 106 MW facility in Jamestown, North Dakota and 180 MW facility in Ellendale, North Dakota were fully operational”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000004/apld2q24earningsrelease.htm) in full (24,819 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apld2q24earningsrelease.htm)

Quote: “the Company's 106 MW facility in Jamestown, North Dakota and 180 MW facility in Ellendale, North Dakota were fully operational”

View cached copy (2026-11-14)Live source ↗