jain.com

7.5 MW HPC data center facility in Jamestown, North Dakota

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2024-08-29
Promised amount
7.5 MW
Current status
stated

The claim, verbatim

Nearing completion of a 7.5 MW HPC facility in Jamestown, ND adjacent to existing 106 MW facility

Source (primary)

Applied Digital 10-K filed 2024-08-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2024-08-30

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility.”

View cached copy (2026-08-31)Live source ↗