Existing Data Center Hosting Capacity
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Operating sites in Jamestown and Ellendale, North Dakota with total hosting capacity of approximately 286 MW
Source (primary)
Applied Digital S-3 filed 2025-12-05 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW.”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The prospectus states directly that the company operates Jamestown and Ellendale, North Dakota sites totaling roughly 286 MW of hosting capacity.
Confirmed in the source:
- Applied Digital operates data center hosting sites in Jamestown and Ellendale, North Dakota
- Total hosting capacity across those sites is approximately 286 MW
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315225026369/forms-3.htm) in full (89,712 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-3 filed 2025-12-05
Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW.”