Jamestown ND facility ramp to 100MW
Company: Applied Digital - Project: Jamestown
The claim, verbatim
The first 55MW at Jamestown, North Dakota came online February 2, 2022. The site now operates at just over 80MW, and the remaining 20MW of its 100MW planned capacity is expected online in the next few weeks.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “The first 55MW of capacity was brought online on February 2, 2022, with current operations at just over 80MW with the remaining 20MW to come online in the next few weeks.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states each element: the 55MW start date, current operations above 80MW, the remaining 20MW timing, and the 100MW planned capacity.
Confirmed in the source:
- The first 55MW at Jamestown, North Dakota came online on February 2, 2022
- The Jamestown site was operating at just over 80MW at the time of the release
- The remaining 20MW was expected to come online in the next few weeks
- Jamestown had an initial planned capacity of 100MW
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,893 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The first 55MW of capacity was brought online on February 2, 2022, with current operations at just over 80MW with the remaining 20MW to come online in the next few weeks.”
confirms Earnings Release
Quote: “The first 55MW of capacity was brought online on February 2, 2022, with current operations at just over 80MW with the remaining 20MW to come online in the next few weeks.”