Jamestown ND facility ramp to 100MW
Company: Applied Digital
The claim, verbatim
The first 55MW at Jamestown, North Dakota came online February 2, 2022. The site now operates at just over 80MW, and the remaining 20MW of its 100MW planned capacity is expected online in the next few weeks.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “The first 55MW of capacity was brought online on February 2, 2022, with current operations at just over 80MW with the remaining 20MW to come online in the next few weeks.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Earnings Release
Quote: “The first 55MW of capacity was brought online on February 2, 2022, with current operations at just over 80MW with the remaining 20MW to come online in the next few weeks.”