5MW specialized processing center energization

Company: Applied Digital - Project: Jamestown

Subject kind
facility timeline
Statement date
2023-01-09
Promised by
2023-03-31
Promised amount
5.0 MW
Current status
verified

What the later record shows

Delivered late

On April 6, 2023, after the Q1 deadline, initial capacity was still expected 'in the next 4-5 weeks'. The July 24, 2023 release says initial capacity at the adjacent Jamestown HPC datacenter, expanded to 9MW, was successfully energized.

“We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”
2023-04-06 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

5MW specialized processing center in Jamestown planned for energization in first calendar quarter of 2023

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release says the new 5MW Jamestown building, adjacent to the existing 100MW facility, was planned for energization in the first calendar quarter of 2023.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (26,009 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 26, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-25 was the source's retrieval date; source published 2023-01-09.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.