5MW specialized processing center energization
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered late
On April 6, 2023, after the Q1 deadline, initial capacity was still expected 'in the next 4-5 weeks'. The July 24, 2023 release says initial capacity at the adjacent Jamestown HPC datacenter, expanded to 9MW, was successfully energized.
“We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”
2023-04-06 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
5MW specialized processing center in Jamestown planned for energization in first calendar quarter of 2023
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release says the new 5MW Jamestown building, adjacent to the existing 100MW facility, was planned for energization in the first calendar quarter of 2023.
Confirmed in the source:
- Applied Digital announced a 5MW specialized processing center in Jamestown, North Dakota
- The 5MW building was planned for energization in the first calendar quarter of 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/49/applied-digital-reports-fiscal-second-quarter-2023/) in full (26,009 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The new building, planned for energization in the first calendar quarter of 2023, will host a new HPC customer for a machine learning application”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
confirms Earnings Release
Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks.”