Company: Applied Digital - Project: Jamestown

This claim was marked delayed on September 14, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2023-05-15
Promised by
2022-02-02
Current status
delayed

The claim, verbatim

First facility in Jamestown, North Dakota brought online and fully operational on February 2, 2022

Source (primary)

Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On February 2, 2022, we brought our first facility online. It is now fully operational.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 424B3 filed 2023-05-16

Quote: “On February 2, 2022, we brought our first facility online. It is now fully operational.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.