North Dakota facility online with 55MW

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2022-04-12
Promised amount
55.0 MW
Current status
stated

The claim, verbatim

First facility in North Dakota is online and providing 55MW of energy as of February 2, 2022

Source (primary)

Applied Digital 424B3 filed 2022-04-13 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Our first facility was constructed in North Dakota and as of February 2, 2022 is online and providing 55MW of energy and services to customers”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document states the North Dakota facility is online providing 55MW as of February 2, 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922045567/tm2124821-27_424b3.htm) in full (539,816 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B3 filed 2022-04-13

Quote: “Our first facility was constructed in North Dakota and as of February 2, 2022 is online and providing 55MW of energy and services to customers”

View cached copy (2026-09-13)Live source ↗