HPC Jamestown Facility Under Construction

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2024-10-28
Promised amount
7.5 MW
Current status
stated

The claim, verbatim

7.5 MW HPC datacenter facility nearing completion in Jamestown, ND

Source (primary)

Applied Digital S-1/A filed 2024-10-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to our 106 MW Data center hosting facility.”

How we checked this

Checked on September 17, 2026. The cited source supports every part of this claim.

The filing says the first of two HPC-focused data centers under construction is a 7.5 MW facility in Jamestown, ND, and that it is nearing completion.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315224042927/forms-1a.htm) in full (173,807 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1/A filed 2024-10-29

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to our 106 MW Data center hosting facility.”

View cached copy (2026-08-31)Live source ↗