HPC Jamestown Facility Under Construction
Company: Applied Digital - Project: Jamestown
The claim, verbatim
7.5 MW HPC datacenter facility nearing completion in Jamestown, ND
Source (primary)
Applied Digital S-1/A filed 2024-10-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to our 106 MW Data center hosting facility.”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The filing says the first of two HPC-focused data centers under construction is a 7.5 MW facility in Jamestown, ND, and that it is nearing completion.
Confirmed in the source:
- The facility is a 7.5 MW HPC-focused data center
- It is located in Jamestown, ND
- It is nearing completion
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315224042927/forms-1a.htm) in full (173,807 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2024-10-29
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to our 106 MW Data center hosting facility.”