GMR customer contract

Company: Applied Digital - Project: Jamestown

Subject kind
customer
Statement date
2022-03-27
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

GMR signed contract for approximately 50% of first facility 100MW capacity

Source (primary)

Applied Digital S-1/A filed 2022-03-28 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “GMR has also been a proponent of our hosting strategy, having signed a contract for approximately 50% of our 100MW capacity”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document states GMR signed a contract for approximately 50% of the 100MW capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922038717/tm2124821-24_s1a.htm) in full (566,257 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1/A filed 2022-03-28

Quote: “GMR has also been a proponent of our hosting strategy, having signed a contract for approximately 50% of our 100MW capacity”

View cached copy (2026-09-13)Live source ↗