Jamestown North Dakota Hosting Facility
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Jamestown facility has 106 MW of hosting capacity
Source (primary)
Applied Digital 424B5 filed 2024-06-17 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Jamestown, North Dakota: 106 MW facility.”
How we checked this
Checked on September 18, 2026. The cited source supports every part of this claim.
The filing lists the Jamestown, North Dakota site as a 106 MW facility.
Confirmed in the source:
- Applied Digital's Jamestown, North Dakota hosting facility is 106 MW
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000167/a06142024ciminitialwarrant.htm) in full (130,571 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B5 filed 2024-06-17
Quote: “Jamestown, North Dakota: 106 MW facility.”