jain.com

Jamestown HPC data center - 7.5 MW

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2024-10-21
Promised amount
7.5 MW
Current status
stated

The claim, verbatim

Applied Digital is building a 7.5 MW HPC data center facility in Jamestown, North Dakota, which is nearing completion

Source (primary)

ARS (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K says the company is building two HPC data centers, the first being a 7.5 MW facility in Jamestown, ND that is nearing completion.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001493152-24-042124/ars.pdf) in full (721,673 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms ARS

Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, ND location adjacent to the Company's 106 MW Data center hosting facility”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-10-21.