Jamestown HPC initial operations in 4-5 weeks
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered; the record does not say when
The July 24, 2023 release says initial capacity at the Jamestown HPC facility was successfully energized. It does not say whether this happened by mid-May 2023.
“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Initial capacity of Jamestown HPC facility expected to come online within 4-5 weeks
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states initial capacity in the new Jamestown HPC facility is expected online in the next 4-5 weeks.
Confirmed in the source:
- Initial capacity of the new HPC facility at Jamestown is expected to come online in the next 4-5 weeks
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks”
confirms Earnings Release
Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”