jain.com

Jamestown HPC initial operations in 4-5 weeks

Company: Applied Digital - Project: Jamestown

Subject kind
facility timeline
Statement date
2023-04-06
Promised by
2023-05-11
Current status
verified

What the later record shows

Delivered; the record does not say when

The July 24, 2023 release says initial capacity at the Jamestown HPC facility was successfully energized. It does not say whether this happened by mid-May 2023.

“The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Initial capacity of Jamestown HPC facility expected to come online within 4-5 weeks

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release states initial capacity in the new Jamestown HPC facility is expected online in the next 4-5 weeks.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “We expect the initial capacity in the new HPC facility to come online in the next 4-5 weeks”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The Company expanded the capacity of its specialized HPC datacenter, adjacent to its existing 100MW Jamestown facility, to 9MW and successfully energized initial capacity at the facility.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 26, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.