Jamestown, ND facility fully contracted capacity
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Jamestown facility has 100MW capacity with entire capacity fully contracted on multi-year contracts
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “Applied Blockchain's first facility is in Jamestown, North Dakota with capacity of 100MW. The entire 100MW of capacity has been fully contracted on multi-year contracts”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release says the first facility in Jamestown has 100MW of capacity, all of it contracted on multi-year contracts.
Confirmed in the source:
- The Jamestown, North Dakota facility has 100MW of capacity
- The entire 100MW at Jamestown is fully contracted on multi-year contracts
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/42/applied-blockchain-reports-fiscal-first-quarter-2023/) in full (25,685 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Applied Blockchain's first facility is in Jamestown, North Dakota with capacity of 100MW. The entire 100MW of capacity has been fully contracted on multi-year contracts”
confirms Earnings Release
Quote: “The entire 100MW of capacity has been fully contracted on multi-year contracts”
confirms Earnings Release
Quote: “The entire 100MW of capacity has been fully contracted on multi-year contracts”
confirms Earnings Release
Quote: “The entire 100MW of capacity has been fully contracted on multi-year contracts”